7 Steps to Improve Bill of Materials

What is a Bill of Materials

Bill of Materials (BOM) is  complete and accurate list of parts for each asset. Having correct BOM is a key element of the technical database. The  list should include all parts that are likely to be used.

Why Are Bill of Materials Important?

With a reliable BOM, planners can focus on providing detailed instructions needed to perform efficient maintenance work. Even with an appreciation for the value, there are numerous roadblocks when undertaking an improvement project. However, BOMs can be systematically improved by following a 7-step process to achieve incredible results.

7 Steps to improve BOMs

bill of materials
7 steps to improve BOM

Step 1: Identify the Current State

Begin with reviewing the hierarchy in your CMMS. Information you should review includes:

We also need to interview key personnel and pull relevant data from the CMMS. We should review:

Consider Key Performance Indicators early in the process.  Relate the current state of BOMs to useful KPIs that can be tracked throughout the project.  Use KPIs that relate to stakeholder’s interests.  Some examples include storeroom inventory reduction, decreased downtime or the amount of time freed up for mechanics.

Step 2: Establish Future Goals

These future goals can be based on benchmarking to best-in-class industry performers or other plants within the organization. Goals can also be based on targets set in conjunction with plant leadership. Link targets to larger organization goals. Take time to document a goal statement that is specific, measurable, achievable, relevant and time bound. The SMART goals will define and improve accountability of the project.

BOM Example

BOM example

STEP 3: Determine Investment

Determine the level of effort required to reach goal.  Build a workflow for the project.  Identify the people and approximate time required to achieve each step.  Look for ways to reduce hand-offs.  Prioritize each goal based on the ultimate value, cost of the investment and time needed to reach the value.

The Return On Investment (ROI) can be calculated for each goal.  Some organizations may require this be done for any project before resources can be used.  Anyone can use this method to compare goals and help prioritize the next steps.   

ROI % = (value-cost)/value x 100

When determining the investment be specific about the types and amount of information needed.  Establish standards for data quality and define the taxonomy to be used.  Spend time with the details of the CMMS.  Identify the fields to be updated to meet the vision and achieve desired results.

BOM Workflow

To help reach the goals (see example above), a workflow will be developed showing the general steps. 

If you have SAP. You need to determine the details needed and a standard developed for the project.

From the project workflow and understanding the details needed in the CMMS, a team of reliability engineers, production resources, mechanics and SAP experts will be needed for a full year to reach the stated goal.

STEP 4: Gather Information

Gather needed information to improve and build BOMs.  This will include existing BOMs and current parts in the CMMS.  Pull relevant data like “where used” reports.  Note when parts were issued and to what equipment.  Collect OEM and vendor manuals and relevant drawings.  Save the collected information in a file structure that matches the equipment hierarchy. 

STEP 5: Correct BOMs

Update and correct BOMs by checking parts lists against manuals and drawings.  If possible, confirm parts listed in the BOMs have good issues against the equipment.  Conduct field tours while the equipment is down and locked out.  Make detailed measurements and pictures to aid in matching part descriptions against actual field information.  Check the storeroom to verify OEMs and labels match part descriptions in the CMMS.

STEP 6: Update the CMMS

Transfer all updates to the CMMS.  This may be done one-off as improvements are made or as part of bulk upload process at the end of the project.

Don’t underestimate the time and resources needed to update the CMMS.  This may require a corporate team or specialized load sheets that will have to be developed and managed.  Despite any challenges, don’t skip this step!  BOM improvement projects that stop at a spreadsheet will fail to provide lasting value.

STEP 7: Continuous Improvement

Train end users on the new BOMs.  Planners, supervisors, and buyers should be aware of updated BOMs and have confidence in the data.  Ensure the equipment hierarchy and individual part details can be navigated.  Include a step in MOC procedures to keep BOMs updated.  Any changes made to field equipment must be reflected in the hierarchy and parts lists. 

BOMs are an element of the technical database that support the overall work management process.  No other element of the technical database adds as much value as BOMs.  They enable planners to quickly order needed parts while primarily focusing on creating detailed instructions for the crews.  This seven-step process can be used to improve BOMs at any plant, mill, or mine.  Having accurate, accessible and applied BOMs is an investment in the future that lead to substantial returns for years to come.

At IDCON, we understand the pressure you face trying to build a reliable plant.
We provide side-by-side reliability and maintenance consulting and training designed to keep your equipment running.

For over 45 years, we’ve partnered with 100s of manufacturing plants around the world to eliminate the costs and the pressure caused by unreliable equipment. And we’d love to do the same for you.

Contact us today to see how we can help you keep your plant running.

Related Articles

Root Cause Failure Analysis

Root Cause Failure Analysis – IDCON’s Root Cause Problem Elimination Process We have named our process for problem solving training and elimination “Root Cause Problem Elimination™” instead of the commonly used

Read More »
Picture of John Sewell

John Sewell

Want weekly Reliability & Maintenance Tips?

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

Best practices. Common sense. Pratical tips.
All designed to help you and your team keep your plant running

IDCON © 2020 All rights reserved

8-step-checklist-preventive-maintenance-program-download
Free Download & Video

8 Steps to Successfully Implement Preventive Maintenance

Reduce your costs with an effective PM program